The City of Vienna has announced the completion of construction on a new main drinking water transmission pipeline in the south of the city, known as the “4th Main Pipeline” (4. Hauptleitung), which is set to enter service in December, according to a statement issued by the municipality on Sunday, November 15, 2026.

A 5.2-Kilometer Pipeline

The new pipeline has a diameter of one meter and stretches over a length of 5.2 kilometers. It connects the end of the 1st Mountain Spring Pipeline (I. Hochquellenleitung) at the Rosenhügel reservoir in the 13th district with the Wienerberg reservoir in the 10th district, supplying drinking water to households in the city’s south while simultaneously strengthening supply security across Vienna.

City Councillor for Climate Jürgen Czernohorszky stated during a visit to the construction site at Altmannsdorfer Anger in the 12th district that major transmission lines are the “arteries” that distribute large quantities of water throughout the city, and expanding them is necessary to supply residents in new urban development areas as part of Vienna’s drinking water strategy.

Tunnel Beneath the Southern Railway Line

Norbert Klicha, Deputy Operational Director of Wiener Wasser, explained that one of the greatest challenges was routing the pipeline beneath the Südbahn railway line, which carries 370 passenger trains daily. A tunnel was built 10 meters beneath the tracks, through which the pipes were inserted via a rail system and connected to the existing network in coordination with the railway company ÖBB.

According to the municipality, the pipeline is currently being flushed and water quality analyzed, and drinking water will only flow through it to households after approval is granted. Remaining surface work will continue until June 2027.

The project is part of the city’s plan to adapt drinking water infrastructure to population growth and climate change, alongside expanding water reservoirs and renovating the pipe network.